Skip to main content

Boiler Top 50 Internal problem and Solution

Boiler Internal Problem and Solution


All boiler internal problem and solution they must follow the manufacturer guideline.

There are 50 boiler internal problem and solutions are given bellow:

1. Leakage:

Problem:


a. The boiler blowdown valve was found to be leaking.
b. Leakage was observed in the level transmitter nipple.
c. Leakage was observed in the welding of the dummy flange nipple.
d. Leakage was found in the feed water suction line.
e. Leakage found in boiler outlet valve.
f. Leakage found in main steam valve and valve in common header.
g. A droplet was observed in the water level gauge glass.
h. Gasket leakages were observed: nipple leakage on top of the boiler, in handhole and manhole.
i. Gas leakage was observed in two joints of the gas line piping.



Solution:

a. The blowdown or drain valve must be replaced.
b. Level transmitter nipple must be tightened.
c. Repair the leakage.
d. Repair the leakage of the feed water suction line.
e. Leakage must be repaired at boiler outlet valve. Ball valve should not be used for boiler steam outlet line.
f. Any leakage in steam valves must be stopped to prevent back steam pressure.
g. The water level gauge glass must be tightened.
h. Replace the defect gaskets.
i. Boiler operator to address leakage and replace/repair as necessary.



2. Refractory lining


Problem:

a. The refractory lining close to burner has defects.

Solution:

a. The lining should be renewed.


3. Safety valve


Problem:

a. Safety valve outlet and vent line are not projected to the boiler room outlet.
b. Safety valve was found to be mounted using a tee joint or mounted on the manhole door.


Solution:

a. Safety valve outlet and vent line must be extended outside of the boiler room.
b. Safety valves must be mounted directly onto the boiler shell.


4. Discharge pump


Problem:

a. During the functional test the discharge pump showed insufficient flow.


Solution:

a. Boiler discharge pump is required to be functional according to manufacturer's guideline.



5. Corrosion


Problem:

a. Inside of the boiler was found to be corroded due to raw water supply.


Solution:

a. Boiler water must be external or internal treated one. Boiler operator should operate the boiler with proper blow down. Avoid the rapid boiler water heating in order to achieve the boiling temperature. Shell thickness and water side bottom end plate thickness are required to be verified and compared with relevant boiler specification.

6. Water drainage

Problem:

a. Inadequate drainage provided from boiler room.

Solution:

a. Provide a appropriate drainage system serving the boiler room, directed externally.


7. Burner 

Problem:

a. Rapid boiling of water at the start of boiler operation.
b. Carbon deposition was found in the burner.

Solution:

a. Provide preventative measures to avoid rapid heating of water in order to reach required temperature.
b. Clean the fuel oil injector periodically.



8. Damaged refractory

Problem:

a. Refractory was found damaged in combustion chamber.

Solution:

a. Repair the refractory in combustion chamber.


9. Feed water quality

Problem:

a. The boiler's feed water quality does not comply with the standards.

Solution:

a. Feed and boiler water quality and conditioning must be verified and monitored. Water TDS, pH value to be maintained as per international or BBR standard to achieve required water quality.

10. Flame monitoring system

Problem:

a. There is no visual flame monitoring system in place.

Solution:

a. A visual flame monitoring system is required to be installed.


11. Flue gas path 

Problem:

a. Flue gas path outlet is not open, flue gas path cannot be observed.

Solution:

a. Provide suitable access to confirm flue gas path.


12. Pressure gauge


Problem:

a. Boiler pressure gauge range too low.

Solution:

a. Boiler pressure gauge range should be twice the boiler's maximum allowable working pressure. Provide appropriate steam pressure gauge for this boiler.



13. Water Level Monitiring


Problem:

a. Water level gauge has no marks for Low Water Level (LWL), Low Low Water Level (LLWL) and High Water Level (HWL).

Solution:

a. Low Water Level (LWL), Low Low Water Level (LLWL) and High Water Level (HWL) must be marked in the water level gauge.



14. Mounting to foundation

Problem:

a. Boiler was found not properly mounted to the base.
b. Foundation of boiler and boiler accessories is inadequate.


Solution:

a. Boiler must be properly mounted to the base according to manufacturer's recommendations.
b. Proper bolt and support to be provided for all foundation as per manufacturer drawing.


15. Salt formation, scale formation

Problem:

a. Salt and scale formation was observed on the water side.
b. Hard scale found in the level transmitter rod.

Solution:

a. Cleaning is required. A water treatment station is to be used and feed and boiler water quality and conditioning must be verified and monitored. The boiler operator should operate the boiler with proper blowdown.
b. Measuring and functional equipment must be cleaned periodically.



16. Soot formation 


Problem:

a. On flue gas side, soot deposition was observed in the furnace as well as inside the fire tube.

Solution:

a. Clean the furnace and inside of the fire tube periodically using air, to prevent excessive soot build-up.


17. Support to pipeline


Problem:

a. The feed water pipeline was found to be lacking proper support.

Solution:

a. Ensure proper support for the feed water pipeline.


18. Water level gauge 


Problem:

a. The water level gauge glass is not protected.
b. Water level gauge vent line was not directed to boiler room outlet.

Solution:

a. Water level gauge glass must be properly protected with proper rod or covered by suitable rectangular protection glasses.
b. Water level gauge vent line should be projected to boiler room outlet.


19. Pipeline routing


Problem:

a. The blowdown outlet pipeline was found to be routed incorrectly (in an upward slope).


Solution:

a. Discuss re-routing with manufacturer.


20. Exhaust gas inlet backplate inspection door


Problem:

a. The exhaust gas inlet backplate inspection door is missing.

Solution:

a. The inspection door must be installed according to the manufacturer's specifications.



21. Carbon deposition 

Problem:

a. Carbon deposition was found in the water tube.

Solution:

a. Install the fuel burner according to the manufacturer's instructions.



22. Improper welding


Problem:

a. Improper welding found between flange and manhole stub joint on the top of the boiler as well as other erection joints.
b. Nozzles have no welded joints on the water side.

Solution:

a. Welding must be rectified by a qualified welder.
b. Suitable welded joints to be provided in order to maintain boiler safety and operational life expectancy.


23. Flue gas path 


Problem:

a. Carbon deposition was found in the flue gas path and fire path.

Solution:

a. Maintain the proper air-fuel ratio as per the manufacturer's data. Clean the flue gas and fire path periodically.


23. Flange thickness


Problem:

a. Top of the flange thickness does not match boiler's specifications.

Solution:

a. Carry out a thickness survey and confirm with manufacturer's data.

Comments

Popular posts from this blog

How to Calculate Heat Rate of Generator Engine?

Types of Power Plant (Technology) Natural Gas Based power plant technology Diesel power plant technology Heat Rate of Engine= Fuel Flow or Fuel burned * Fuel Heating Value / Power Output 1 Liter Diesel = 0.85 Kg Example: Heat Rate of Diesel Generator at 100% Load Engine Model- 2506A-E15TAG2 Engine Capacity=400 eKW Fuel Consumption=84 L = 71.4 Kg Electrical Energy Output = 400 KW Heating Value of Diesel = 42.5 MJ/Kg Heat Rate of Engine= Fuel Flow or Fuel burned * Fuel Heating Value / Power          Output Heat Rate of Engine = 71.4 Kg * 42.5 MJ/Kg /400KW   Heat Rate of Engine =7.58 MJ/KWH Heat Rate of Gas Generator at 100% Load Engine Model- VHP5904LTD Engine Capacity= 900 eKW Fuel Consumption= 271 Nm 3 Electrical Energy Output= 900 KW Fuel Consumption= 0.28 Nm3/KWH Heating Value of Natural Gas= 35.22 MJ/ Nm 3 Heat Rate of Engine= Fuel Flow or Fuel burned * Fue...

Packing, Seals and Gaskets

Packing, seal and gasket resists the flow of fluid from machinery face, head, joint and machinery gap or clearance. Packing materials: Fiber, asbestos, cotton, synthetic materials, plastic, Teflon, graphite etc. Packing structure: Twisted, Braided and Consolidated. Gasket:             A gasket is a mechanical seal that fills the space between two mating surfaces, generally to prevent leakage from or into the joined objects while under compression. Gaskets allow " less-than-perfect " mating surfaces on machine parts where they can fill irregularities. Gaskets are commonly produced by cutting from sheet materials, such as gasket paper, rubber, silicone, metal, cork, felt, neoprene, nitrile rubber, fiberglass, or a plastic polymer (such as polychlorotrifluoroethylene)                        ...

Why a dc generator fails to build up voltage?

How can the problem be remedied : No residual magnetism, reversed field connection and high resistance of field circuit are responsible for the failure of build up process of a dc generator. The factors are explained below: No residual magnetism:    For the starting build up process requires some residual magnetism in the magnetic circuit then no voltage will be generated that can produce current flow through field circuit. Reversed field connection:    The voltage induced inside the coil of field circuit due to residual magnetism that can permit the flow of current. For the following direction of this flux will be created and the direction of this flux will be same direction as the residual flux. If the field connections are reversed the lines of flux produced by current flow will oppose the residual flux, as a result generate voltage will decrease rather than increase. So voltage build up process failed. Field circuit resistance ...

what is the difference between long shunt and short shunt dc generator?

How do they differ from normal generator?    Draw their V-I characteristics and explain them? In short shunt connection the shunt field is connected directly across the armature terminals and the armature connection equals the sum of the shunt field current plus the load current . In this instance the load current flow s through the series field winding so that the load current and series field current are one and same.              In long shunt connection the voltage across the shunt field is the same as the terminal voltage of the generator and current in the armature will be the current in the series field. The armature current equals the shunt field current plus the load current.   A shunt generator has the field circuit connected directly across the armature. As more devices connected in parallel the load on the generator increases that the generator current increases which...

Therbligs and Basic 17 motion name of therblig

Therbligs : A graphical representation of the co-ordinated activities of an operators body members. These activities ar described in terms of basic or fundamental motions known as therbligs.                                         At the time Frank Gilbreth was doing his work in the field of motion study, he also concluded that any manual activity could be described in terms of 17 fundamental motions. This comparable to our being able to describe every word in the English language in terms of some of the 26 letters of the alphabet. Each of these fundamental motions is called a Therblig. Basic 17 motion name of Therblig : Name of Therblig Letter abbreviation Search Select Grasp Transport empty Transport loaded ...

Which type of Battery connection Series or Parallel Connection is used for Diesel Generator?

Diesel Generator Battery Connection Batteries can emit explosive gases.     To reduce the possibility of personal injury, always ventilate the compartment before servicing the batteries. To remove the possibility of arching, remove the negative battery cable is first and attach the negative battery last. When using jumper cables to start the engine make sure to connect the cables in parallel Positive to positive and negative to negative. When using external electrical source to start the engine, turn the disconnect switch to the OFF position. Remove the key before attaching the jumper cables. To avoid damage to engine parts do not connect jumper starting or battery charging cable to any fuel system or electronic component. Battery Parallel Connection: The accompanying illustration shows a typical parallel battery connection. This arrangement doubles the cranking amperage. Battery Series Connection: This illustration sh...

Various Methods of Drawing Flow Nets

  1.       Hydraulic models: a.        Streamlines can be traced by injecting a dye in a seepage model or Heleshaw apparatus. b.       They by drawing equipotential lines the flow net is completed. 2.       Analytical Method: a.        It is only applied to problems with simple and ideal boundaries conditions. b.       The equation corresponding curve Ç¿ and Ñ° are first obtained and the same are plotted to give the flow net pattern for the flow of fluid between the given boundary shape. 3.       Electrical Analogy Method: This method based on the fact that the flow of fluids and flow of electricity through a conductor are analogus. These two systems are similar in the respect that electric potential is analogus to the velocity potential. The electric current is analogus to...

“Equalizer connection is needed in lap winding armature but not in wave winding “ why ?

 The equivalent circuit of a four point – pole dynamo with a simplex winding. The voltage induced in each path is assumed to both to be same and should be if the reluctance of each magnetic path is the same, so that the lines of flux cut by each inductor of each path are the same. However wear of the bearings or deflection of the armature shaft may cause the armature to be closer to some poles and farther from others, thus changing the length of the air gap, and therefore the reluctance of the magnetic circuits of the poles is not identical. This factors cause the voltage in the materials making up the magnetic circuit. These factors cause the voltage in each parallel path differ, and the unequal voltages in turn cause flow of a circulating   current through the windings and brushes , undue heating of the armature and waste the power. To reduce the circulating current, points on the winding which should be at the same potentials are brought to the same potentials by c...

what is PIV drive? Why is PIV drive more effective than any other system of drive?

PIV Drive: A stepless drive where the transmission of torque takes place infinitly variable without   slip is called PIV drive. There are some advantages of PIV drive: there is no slip in the transmission of power. Maximum transmission of power. Speed can be changed at running condition Any range of slip can be obtain It give constant cutting speed for the above reason PIV drive is more effective than any other system   of drive

What are the main components of Automobile?

  There have five basic parts for Automobile and they are given bellow: 1.      Engine: Engine which is known to all as a power plant. Engine is the source of power which makes the car wheels rotate and the car move where it supply power to lubricating, fuel, electric and cooling systems. 2.      Frame:   Frame support the engine, body and wheels. 3.      Power train: Power train transmit the power engine to the car wheels where its contain clutch, transmission, propeller shaft, axles and differential.  4.      Car Body 5.      Car body accessories: A car body accessory contains the heater, lights, radio, windshield wiper and convertible top raiser.